Run-of-River Hydro » Typical Project Progression

Typical Project Progression

Below is a guideline illustrating the typical progression of a project through all phases of planning and construction. Shawater Limited offer expert guidance and assistance at all stages. (Note: Precise schedule may differ depending upon specific circumstances encountered)

Spring Yr1Grid Connection application
Produce Scheme Profitability Forecast
Install River Level Logger
Carry out flow gauging
Consult environmental advisors
Summer Yr1Carry out flow gauging
Undertake environmental surveys
Autumn Yr1Carry out flow gauging
Undertake environmental surveys
Winter Yr1Produce Environmental Statement
Carry out flow gauging
Spring Yr2Finalise Environmental Statement
Calculate Abstraction Regime
Submit Planning Application
Summer Yr2Structural Engineering Design
Grid Connection Design & Approval
Autumn Yr2Evaluate potential Contractors, Pre-tender enquiry
Obtain quotations for equipment and materials
Winter Yr2Obtain Abstraction Licence
Obtain Planning Permission
Appoint Construction Management Team
Produce and sign Contract Documents
Prepare Construction Method Statement
Spring Yr3Organise Equipment Storage
Appoint Environmental Liaison Officer and Archaeologist
Begin Construction
Summer Yr3Construction
Equipment arrivals
Autumn Yr3Equipment arrivals
Scheme Commissioning
Power Generation
OngoingPerformance monitoring
Environmental monitoring